Item Coversheet
AGENDA ITEM INFORMATION

ITEM:  CONTRACT – SPRING MILL PUMP STATION IMPROVEMENT – PIPING CONTRACT

Consider for recommendation to the Board of Commissioners award of a contract for Spring Mill Pump Station Improvement – Piping Contract to the following low bidder in accordance with bids received on Tuesday, February 26, 2019 at 11:00 A.M. prevailing time and the recommendation of the Chief Financial Officer with the approval of the Township Engineer and the Director of Public Works:

 

PSI Pumping Solutions, Inc.

 

 

 

Total Lump Sum Bid

$175,600.00

Total Bid Contingency Items (C-1 – C-4)

    10,600.00

Total Bid

$186,200.00


PUBLIC COMMENT
ADDITIONAL INFORMATION:

Funds are available through the Capital Projects Fund – Spring Mill Pump Station Improvements Project #4751.  The construction budget for this project was $190,000.  This bid award is $3,800 or 2% less than the construction budget.


ATTACHMENTS:
DescriptionType
CONTRACT – SPRING MILL PUMP STATION IMPROVEMENT – PIPING CONTRACTBid Tabulation
CONTRACT – SPRING MILL PUMP STATION IMPROVEMENT – PIPING CONTRACTBackup Material
REVIEWERS:
DepartmentReviewerActionDate
FinanceKelley, JodyApproved3/15/2019 - 11:54 AM