AGENDA ITEM INFORMATION
ITEM: CONTRACT - KNOX BASIN IMPROVEMENTS
Consider for recommendation to the Board of Commissioners award of a contract for Knox Basin Improvements to the following responsible low bidder in accordance with bids received on Thursday, June 6, 2019 at 11:00 A.M. prevailing time and the recommendation of the Chief Financial Officer with the approval of the Director of Public Works and Township Engineer:
|
|
JMC Contractors, Inc.
|
|
|
|
Total Lump Sum Bid:
|
$279,810.00
|
Total Bid: Contingency Items (C-1 to C-8)
|
5,895.00
|
Total Bid:
|
$285,705.00
|
|
|
|