Item Coversheet
AGENDA ITEM INFORMATION

ITEM:  CONTRACT – SOUTH ARDMORE PARK PERIMETER PATH

Consider for recommendation to the Board of Commissioners award of a contract for South Ardmore Park Perimeter Path to the following low bidder in accordance with bids received on Thursday, January 18, 2018 at 11:00 A.M. prevailing time and the recommendation of the Chief Financial Officer with the approval of the Township Engineer and the Director of Public Works and Director of Parks and Recreation:

 

JMC Contractors, Inc.

 

38 Stephen Drive

 

Glen Mills, PA 19342

 

 

 

Total Lump Sum Bid

$ 111,795.00

Total Bid Alternate Items (AA-1.1 – AA-1.4)

    29,280.00

Total Bid Alternate Items (AA-2.1 – AA-2.8)

    18,130.00

Total Bid

$159,205.00

PUBLIC COMMENT
ADDITIONAL INFORMATION:

Funds are available through the Capital Projects Fund – Bicycle and Pedestrian Path System Implementation Project #4477.  The construction budget for this project was $161,000.  This bid award is $1,795 or 1% less than the construction budget.

ATTACHMENTS:
DescriptionType
CONTRACT – SOUTH ARDMORE PARK PERIMETER PATHBid Tabulation
CONTRACT – SOUTH ARDMORE PARK PERIMETER PATHBackup Material